STRUCTURAL EXCAVATION AND BACKFILLING SECTION 207 121 4. Structural and pipe backfilling at the contract unit price per cubic yard. The Department will consider that price and payment as constituting full compensation for placing and compacting all approved backfill.
invert. The Department will not pay for backfill or backfilling areas between the over excavated subgrade and 12 -inches below the proposed pipe invert.
will pay the unit price plus the additional percentage according to the pay limits provided in Table 207.5 -1 below. Table 207 .5 -1. Payment for Additional Excavation Depth Depth Lowered Additional Percent More Than (feet) Not Over (feet) 0 5 25 5 8 60 8 10 100
ITEM DESCRIPTION UNIT 207001 PIPE, CULVERT AND STRUCTURE BACKFILLING CY 207002 PIPE, CULVERT AND STRUCTURE EXCAVATION CY 207010 ROCK EXCAVATION FOR STRUCTURES AND TRENCHES CY 207011 ROCK EXCAVATION FOR STRUCTURES AND TRENCHES (FIXED PRICE) CY 20702 0 STRUCTURAL BACKFILL, BORROW TYPE B, PROVIDING ONLY CY 20702 1 STRUCTURAL BACKFILL, BORROW TYPE C, PROVIDING ONLY CY FLOWABLE FILL SECTION 208 122 SECTION 208 — FLOWABLE FILL
208.1Description.
This work consists of providing and placing flowable fill.
208.2Materials.
calendar days before use. Include test data characteristics of the ash leachate as determined by the Toxicity Characteristics Leaching Procedure (TCLP) in acc ordance with EPA SW -846, with respect to leachate metals.
208.3Construction.
208.3.1 Plant and Equipment Requirements. Provide flowable fill produced only in batching plants in accordance with Section 1022.
2 Transportation
Transport flowable fill in ready -mix trucks or as approved by the engineer. Place the flowable fill within 3-hours of mixing water with the dry materials.
3 Placement
ends of the pipe are sufficiently plugged upon completion of the work .
maximum allowable lift is 5 -feet deep unless otherwise directed by the engineer. Allow each lift to cure until it is self -supporting before placing additional lifts or other loads.
means of restraint required to ensure proper alignment when using flowable fill as backfill for pipes. FLOWABLE FILL SECTION 208 123 I. Maintain all confining and supporting structures, protective covers, and barriers until the flowable fill is self -supporting. Shrinkage of the flowable fill as it cures may require additional backfill with other material. Protect flowable fill from direc t contact with vehicular traffic and from prolonged exposure to rain or running water.
208.4Method of Measurement.
the approved limits of the fill location. The Department will measure pipe trenches in accordance with Section 207.4.
208.5Basis of Payment.
The Department will pay for flowable fill at the contract unit price per cubic yard. Price and payment will constitute full compensation for:
ITEM DESCRIPTION UNIT 208000 FLOWABLE FILL CY BORROW SECTION 209 124 SECTION 209 — BORROW
209.1Description.
This work consists of providing and placing borrow material from approved offsite borrow sources.
209.2Materials.
Borrow Section 1001
209.3Construction.
209.3.1 Borrow Sources.
material from an offsite borrow source. Submit a description of the approved material limits within the offsite borrow source and the method of excavation for a pproval by the Department’s Materials and Research Section.
the engineer’s written permission.
borrow source, and removed the overburden. Implement the physical control plan and obtain approval before the Department cross -sections the source. Control m ethods may include fencing, earth berms, guardrails, or other physical barriers. If the offsite borrow source is fenced, provide a padlocked gate at the entrance. The Department will retain the padlock key.
that allows accurate measurement. Prevent water from collecting or standing within the excavated borrow area. 209.3.2 Source Testing. The Department will assist the contractor in determining the quality and quantity of material from sources the contractor proposes to use. The Department will perform soil analysis tests. The Department will sample and test the offsite borrow source. 209.3.3 Borrow Placing and Compacting. Place and compact borrow in accordance with Section 202.3.8. 209.3.4 Providing Borrow for Utility Backfill.
agreed to by the contractor, the utility, and the engineer.
organizations involved will backfill utility trenches in accordance with Section 202.3.8. The Department will not require proof rolling.