STONE SECTION 302 130 SECTION 302 — STONE
302.1Description .
This work consists of providing, placing, and compacting stone.
302.2Materials.
302.3Construction.
prevent segregation.
302.4Method of Measurement.
The Department will measure stone as the number of tons of stone placed and accepted. The Department will determine weight in accordance with Section 109.1.
302.5Basis of Payment.
The Department will pay for stone at the contract unit price per ton. Price and payment constitute full compensation for preparing, providing, placing, and compacting all materials. ITEM DESCRIPTION UNIT 302002 DELAWARE NO. 3 STONE TON 302003 DELAWARE NO. 8 STONE TON 302004 DELAWARE NO. 10 STONE TON 302005 DELAWARE NO. 57 STONE TON BITUMINOUS PAVEMENT SECTION 401 131 DIVISION 400 — BITUMINOUS MATERIALS
401.1Description .
This work consists of providing, placing, and compacting bituminous pavement.
401.2Materials .
401.3Construction .
Conduct a pre -paving meeting to discuss joint layout, material delivery, striping layout, maintenance of traffic for paving, and equipment. Include the engineer, the Department’s Materials & Research Section, and other appropriate parties.
Develop the JMF in accordance with Section 1014 and submit test results for review a minimum of 30 calendar days before application. Include aggregate type and gradation and percentages of polymer -modified emulsion, water, and cement by dry aggregate weigh t.
Deliver no less than 100 tons per hour to the project site or as approved by the engineer.
solution, or other approved release agent to prevent the bituminous mixture from adhering to the truck bed.
holes, that will cover the truck bed from front to back and will overlap the sides and rear of the truck body.
dam.
does not reach over the back of the body, straps on the rear of body are also required.