CONDUIT SECTION 831
481 SECTION 831 — CONDUIT
831.1Description.
This work consists of providing and placing or removing conduit.
831.2Materials.
831.3Construction.
proposed conduit arc.
wells, and risers. Seal the conduit to provide a liquid tight connection. The Department will not require sealant for traffic signal or fiber optic conduit.
finished grade.
of the pull rope after placing the cable in the conduit.
required by the Standard Construction Details. Do not extend conduit into a junction well any more than 3 -inches.
has been used to clear all foreign matter 831.3.1 Galvanized Steel Conduit.
CONDUIT SECTION 831
482 B. Provide enough thread to ensure that the sections of conduits, when coupled together, will butt together providing a watertight joint.
when a standard coupling will not work. Do not use a threaded union in a conduit run when placing conduit by the driven method. Do not use a threadless couplin g or a split -bolt coupling for direct buried conduit. 831.3.2 HDPE -SDR 13.5 Conduit. Connect lengths of HDPE conduit with irreversible fusion couplings. Do not use mechanical or removable couplings. 831.3.3 PVC Schedule 80 Conduit
flared end of the adjoining length of conduit or use a coupling.
waterproof link.
conduit segment to mate with the normal end of the other segment, if approved by the engineer. Place caps on the ends of conduits after using compressed air to clear debris from the conduit. 831.3.4 Directional Bore Installation.
the existing pavement. Do not exceed the outside diameter of the conduit being installed by more than 1 -inch. Pump cement grout into the void in cases where the directional bore exceeds the outside diameter by more than 1-inch.
end of the conduit and use compressed air to clear debris before inspection. 831.3.5 Open Cut Installation.
diameter no less than 2 -inches under existing pavement. Obtain the engineer’s approval for open cutting roadways not shown as open cut in the contract. Remove cut pavement and replace the pavement after conduit installation.
accordance with Sections 401 or 503. Remove pavement in accordance with the Standard Construction Details . The engineer will decide if the excavated material is suitable or unsuitable for backfill. Provide new backfill material, if the engineer decides the excavated material is unsuitable for backfill. Excavate to a depth in accordance with Section 831.3 and the contract. Place conduit and spare conduit in the trench a nd terminate in a junction well or base, in accordance with the Standard Construction Details .
accordance with Section 207. Install underground warning tape over the conduit approximately 12-inches below the final grade. Compact the final lift of fill material to the planned final grade. Patch open trenches in accordance with Section 40 1 for bituminous pavements or Section 503 for rigid pavements. CONDUIT SECTION 831
483 831.3.6 Unpaved Trench Installation.
trench and terminate into a junction well or base in accordance with the Standard Construction Details .
accordance with Section 207. Install underground warning tape over the conduit approximately 12-inches below the final grade. Compact the final lift of fill material to the planned final grade. Apply topsoil and seed t o t he disturbed area in accordance with Section 908. 831.3.7 Conduit Installation on Structures. Install conduit on structures, in accordance with the contract, using approved conduit hangers and anchors. Drill anchors into concrete, brick, stone, steel, or wood, and attach the conduit hangers, spaced no more than 36 -inches apart. Use sweeping bends to provide 90 -degree turns in the conduit run. 831.3.8 Pole Riser Shields. Install nonmetallic pole riser shields on wood poles in a straight vertical line. Use an adapter if the nonmetallic pole riser is not the same size as the conduit the riser attaches to. Attach the riser shield to the pole with 1/4-inch x 1 1/2 -inch galvanized lag bolts with washers. Install lag bolts spaced no more than 36 inches apart on both sides of the riser shield and in the topmost and bottom most set of slots. 831.3.9 Conduit Removal from Wood Poles. Remove conduit, straps , nails, or lag screws in a manner that does not damage or disturb other conduits on the pole. Dispose of materials in accordance with Section 106.8.
831.4Method of Measurement.
liquid tight conduit, and nonmetallic pole riser shields as the number of linear feet provided, placed, and accepted.
directional bore along the path of the bore from the point where it is not possible to trench to a point where trenching can resume.
trench, on wood poles, and on structures along the conduit.
of linear feet of conduit removed.
831.5Basis of Payment.
linear foot for the pay items listed below. Price and payment constitute full compensation for providing and placing conduit , backfill and backfilling, and duct sealant .
unit price per linear foot for the pay items listed below. Price and payment constitute full CONDUIT SECTION 831
484 compensation for removing conduits and attachment hardware and disposing of removed materials. ITEM DESCRIPTION UNIT 831001 PROVIDE AND INSTALL UP TO 3” FLEXIBLE METALLIC -LIQUID TIGHT CONDUIT LF 831002 PROVIDE AND INSTALL UP TO 4” SCHEDULE 80 HDPE CONDUIT (BORE) LF 831003 PROVIDE AND INSTALL UP TO 4” SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831004 PROVIDE AND INSTALL UP TO 4” SCHEDULE 80 PVC CONDUIT (TRENCH) LF 831005 PROVIDE AND INSTALL UP TO 4” SCHEDULE 80 PVC CONDUIT (ON STRUCTURE) LF 831006 PROVIDE AND INSTALL UP TO 4” GALVANIZED STEEL CONDUIT (TRENCH) LF 831007 PROVIDE AND INSTALL UP TO 4” GALVANIZED STEEL CONDUIT (BORE) LF 831008 PROVIDE AND INSTALL UP TO 4” GALVANIZED STEEL CONDUIT (OPEN CUT) LF 831009 PROVIDE AND INSTALL UP TO 4’ GALVANIZED STEEL CONDUIT (ON STRUCTURE) LF 831010 PROVIDE AND INSTALL UP TO 4” NONMETALLIC POLE RISER SHIELD LF 831011 REMOVAL OF CONDUIT FROM WOOD POLE LF 831012 PROVIDE AND INSTALL UP TO 6” SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831013 PROVIDE AND INSTALL 4" SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831014 PROVIDE AND INSTALL 3" SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831015 PROVIDE AND INSTALL 2 1/2" SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831016 PROVIDE AND INSTALL 2" SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831017 PROVIDE AND INSTALL 1" SCHEDULE 80 PVC CONDUIT (OPEN CUT) LF 831018 PROVIDE AND INSTALL 1” FLEXIBLE METALLIC LIQUIDTIGHT CONDUIT LF 831019 PROVIDE AND INSTALL 2” FLEXIBLE METALLIC LIQUIDTIGHT CONDUIT LF 831020 PROVIDE AND INSTALL 3” FLEXIBLE METALLIC LIQUIDTIGHT CONDUIT LF 831021 PROVIDE AND INSTALL 4” FLEXIBLE METALLIC LIQUIDTIGHT CONDUIT LF 831022 PROVIDE AND INSTALL 1" SCHEDULE 80 PVC CONDUIT (TRENCH) LF 831023 PROVIDE AND INSTALL 2" SCHEDULE 80 PVC CONDUIT (TRENCH) LF 831024 PROVIDE AND INSTALL 2 1/2" SCHEDULE 80 PVC CONDUIT (TRENCH) LF 831025 PROVIDE AND INSTALL 3" SCHEDULE 80 PVC CONDUIT (TRENCH) LF 831026 PROVIDE AND INSTALL 4" SCHEDULE 80 PVC CONDUIT (TRENCH) LF 831027 PROVIDE AND INSTALL 1" SCHEDULE 80 PVC CONDUIT (ON STRUCTURE) LF 831028 PROVIDE AND INSTALL 2" SCHEDULE 80 PVC CONDUIT (ON STRUCTURE) LF 831029 PROVIDE AND INSTALL 2 1/2" SCHEDULE 80 PVC CONDUIT (ON STRUCTURE) LF 831030 PROVIDE AND INSTALL 3" SCHEDULE 80 PVC CONDUIT (ON STRUCTURE) LF 831031 PROVIDE AND INSTALL 4" SCHEDULE 80 PVC CONDUIT (ON STRUCTURE) LF 831032 PROVIDE AND INSTALL 1” GALVANIZED STEEL CONDUIT (TRENCH) LF 831033 PROVIDE AND INSTALL 2” GALVANIZED STEEL CONDUIT (TRENCH) LF