DRAINAGE STRUCTURES SECTION 602 180 602005 DRAINAGE INLET, 48” X 48” EACH 602006 DRAINAGE INLET, 66” X 30” EACH 602007 DRAINAGE INLET, 66” X 48” EACH 602008 DRAINAGE INLET, 66” X 48” EACH 602009 DRAINAGE INLET, 72” X 24” EACH 602010 DRAINAGE INLET, 72” X 48” EACH 602011 DRAINAGE INLET, 72” X 72” EACH 602012 DRAINAGE INLET, SPECIAL EACH 602013 DRAINAGE INLET, SPECIAL LS 602030 MANHOLE, 48” X 30” EACH 602031 MANHOLE, 48” X 48” EACH 602032 MANHOLE, 66” X 30” EACH 602033 MANHOLE, 66” X 48” EACH 602034 MANHOLE, 66” X 66” EACH 602035 MANHOLE, ROUND EACH 602036 MANHOLE, SPECIAL EACH 602037 MANHOLE, SPECIAL LS 602060 JUNCTION BOX, 48” X 30” EACH 602061 JUNCTION BOX, 48” X 48” EACH 602062 JUNCTION BOX, 66” X 30” EACH 602063 JUNCTION BOX, 66” X 48” EACH 602064 JUNCTION BOX, 66” X 66” EACH 602065 JUNCTION BOX, SPECIAL EACH 602066 JUNCTION BOX, SPECIAL LS 602067 CONVERTING DRAINAGE INLET TO JUNCTION BOX EACH 602100 DRAINAGE INLET GRATE(S) EACH 602101 DRAINAGE INLET FRAME(S) EACH 602102 MANHOLE GRATE(S) EACH 602103 MANHOLE FRAME(S) EACH 602130 ADJUSTING AND REPAIRING EXISTING DRAINAGE INLET EACH 602131 ADJUSTING AND REPAIRING EXISTING DOUBLE DRAINAGE EACH 602132 ADJUSTING AND REPAIRING EXISTING MANHOLE EACH 602133 ADJUSTING AND REPAIRING EXISTING JUNCTION BOX EACH
TEMPORARY WORKS SECTION 604 181 SECTION 604 — TEMPORARY WORKS
604.1Description.
This work consists of constructing and removing temporary facilities used to perform the work.
604.2Materials.
604.3Construction.
604.3.1 Submittals.
advance of beginning the work, in accordance with Section 105.4. Include materials list, fabrication and erection details, jacking support plan, design calculations , and supporting data in sufficient detail to allow a structural review of the proposed design of a temporary work. Use a registered Delaware professional engineer to design and seal drawings and calculations for the temporary works in accordance with AASH TO LRFD Bridge Design Specifications, the Guide Design Specifications for Bridge Temporary Works, or to other design requirements in accordance with the contract.
joint patterns, and details for wrapping the form liner around corners in accordance with Section
604.3.3Submit a form liner sample
traveled way and the shoulder, is as follows:
The Department will not allow any part of the temporary works system to encroach on clearance restrictions over the roadway and shoulders.
works in conformance with the approved working drawings. 604.3.2 Falsework and Formwork.
forms true to the dimensions, lines, and grades of the structure before and during concrete placement.
alignment and camber indicated for the permanent structure. Allow for minor adjustments during concrete or structural steel placement. Attach an approved indicator to the forms to TEMPORARY WORKS SECTION 604 182 detect settlement, movement, or deflection in the falsework. Provide for accurate measurement of falsework settlement during concrete placement and curing.
uniform texture. Use rigid forms to ensure a concrete surface tolerance of less than 1/8 -inch in 5-feet when checked with a 5 -foot straightedge or template. Fillet sharp corners with 3/4 -inch chamfer strips. Bevel or chamfer at projections, such as copings, to ensure easy removal.
and tie girders to resist forces that could cause rotation or torsion in the girders. Do not weld falsework support brackets or braces to structural steel members or reinforcing steel unless specified in the contract or allowed by the engineer.
opening in the forms for cleaning immediately before placing the concrete. For thin wall construction, daylight forms at intervals no greater than 10 -feet vertically to permit free access to the forms for working, vibrating the concrete, and inspection.
clearance between the falsework and the traveled way.
inch below the concrete surface. If the contract specifies epoxy -coated reinforcing steel, use embedded ties, anchorages, or spreaders of corrosion -resistant material or coated with a dielectric material. Design fittings for metal ties to minimize the size of the cavities remaining after removal.
in the concrete.
and box beams. Fabricate the tubes with waterproof outside layers. Protect tubes from the weather. Place tubes using methods that prevent distortion or damage before concrete placement. Cover the ends of tube forms with mortar -tight and waterproof caps to prevent concrete from entering the tubes during concrete placement. Use a pre -molded rubber joint filler, 1/4-inch thick, around the perimeter of the caps to allow for expansion. Provide a PVC vent tube at the location indicated in the contract, to provide drainage from the voids. Trim the vent tubes to within 5/8 -inch of the bottom surface of the finished concrete after removing the exterior form. Anchor or ti e tube forms to prevent displacement of the tubes during concrete placement. The contractor may use styrofoam blocks instead of cardboard tubes provided they are anchored to prevent displacement during pouring.
TEMPORARY WORKS SECTION 604 183 2. When removing falsework and forms:
sheet piles as follows:
ii. 24-inches below the original ground or finished grade outside of roadbeds and 24-inches below the established limits of any navigation channel .
of utilities shown in the contract. 604.3.3 Form Liners.
defects and that do not compress more than 1/4 -inch when poured vertically at a rate of 10 feet per hour;
damage or weakness in the substrate; and
or on a series of panels.
finished concrete surface. Offset horizontal joints between adjacent vertical stacks of form liner panels.
surface. Avoid creating visible vertical or horizontal seams or conspicuous form marks within the finished concrete surface.
TEMPORARY WORKS SECTION 604 184 1. When called for in the contract, construct sample panels to demonstrate the form liner patterns. Locate the sample panel as close as practicable to the structure for use as a basis of comparison to the work constructed on the finished structure.
test section.
proposed structural elements using form liners.
sections until the engineer approves an acceptable unit.
recommendations and with less than a 1/4 -inch seam.
accordance with the manufacturer's recommendation.
application of the aesthetic stain.
and joint size as the approved sample panel or test section.
and color of the surrounding concrete. 604.3.4 Jacking Bridge.
plate attached to each jack.
The engineer may waive the radiographic and ultrasonic inspection requirements if the welds appear satisfactory after a visual inspection.
contract dimensions and requirements before allowing jacking operations to start.
ensure the safety of the structure.
system with a chart that allows conversion of the dial reading into pounds.
supports after jacking. TEMPORARY WORKS SECTION 604 185 6. Repair areas of the existing structure damaged during the jacking operation in accordance with 604.3.5 Protective Shield.
against damage from falling demolition or construction debris.
removal process, unless otherwise noted in the contract. Supplement the shields with additional enclosures of tarpaulins or wire mesh, as necessary, to ensure against materials, tools, equipment, and othe r objects dropping below the level of the shield. Ensure that the floor and sides of the shield have no cracks or openings through which material particles may fall. Install all connections of the protectives tructures to the steel work of existing bridge by means of clamps or other approved devices. Do not drill holes in, or weld anything to, the existing steel.
shield.
604.3.6 Cofferdams.
against flooding damage during the concrete curing period. Provide a cofferdam to obtain, as nearly as possible, a water -free work area large enough to allow f or a sump and for form inspection.
Portions of cofferdams may remain in place in accordance with Section 604.3.2.D when approved by the engineer. 604.3.7 Shoring.
construction activities. Provide rigid and strong shoring to safely support the imposed loads and allow for construction activities adjacent to facilities remaining i n service, as required in the contract.
the engineer. 604.3.8 Wetland Access.
Access wetlands and subaqueous lands using temporary matting to support equipment loads. Use timber or composite material for temporary mats. Use a matting system with interlocking panels to distribute loads and anchored to resist high water flows.
TEMPORARY WORKS SECTION 604 186 1. Clear only trees directly in conflict with the needed access. Flag these trees and obtain approval from the engineer before beginning the clearing operation.
using a winch or other similar equipment.
perform stump removal. Do not grub in wetland areas.
extend beyond the edges of the geotextile fabric. Determine the thickness and type of stone capable of supporting the anticipated equipment.
areas to their preconstruction condition. 604.3.9 Temporary Works Removal. Remove and retain or dispose of materials used for temporary works after completing the work. If construction of temporary works disturbed the area where the temporary works were placed, restore the area to its original or planned condition.
604.4Method of Measurement.
shoring, or wetland access.
area that the contractor used the form liners on. The Department will measure the approved sample panel as an additional concrete surface area.
604.5Basis of Payment.
requiring the use of the temporary work.
TEMPORARY WORKS SECTION 604 187 D. Price and payment for protective shield constitute full compensation for:
will pay the cost of the materials left in place.
to stabilize structural excavation as incidental to Section 207.
maintaining, and removing temporary matting materials and for restoring the wetland access area to preconstruction conditions.
ITEM DESCRIPTION UNIT 604000 JACKING BRIDGE LS 604001 PROTECTIVE SHIELD LS 604002 COFFERDAMS LS 604003 SHORING LS 604004 WETLAND ACCESS LS 604005 FORM LINERS SF
DRIVEN PILES SECTION 605 188 SECTION 605 — DRIVEN PILES
605.1Description.
This work consists of providing, installing and dynamically testing foundation piles.
605.2Materials.
605.3Construction.
605.3.1 Submittals.
position during concrete placement.
pile driving system to the engineer for approval. Use Figure 605.3C -1 DelDOT Pile and Driving Equipment Data Form.
per minute for the hammer in use.
conduct load tests, record all data, and provide test result reports to the engineer.
interpreting dynamic pile testing.
collecting the data has documented experience on at least 10 previous projects with similar pile