B
HomeLibrariesCopilotSearchProjectsBookmarks
FeedbackHelp Desk
Libraries
Building Codes
Code LibraryIBC — BuildingIRC — ResidentialIFC — FireIPC — PlumbingIMC — MechanicalIFGC — Fuel GasIECC — EnergyNEC — ElectricalModel Codes
Specifications
CSI SpecificationsDOT SpecsTransit SpecsUSACE
Standards
TransportationRailroadFire SafetyAccessibilityStructural
Tools & References
DiagramsAssembliesProductsCalculatorsChecklistsPermits
PricingLog in
Electrical (16000-16999)

905001 SILT FENCE LF

DE · 2025 Standard SpecificationsBook pages 595598View official source ↗

DEWATERING PRACTICES SECTION 906 585 SECTION 906 — DEWATERING PRACTICES

906.1Description.

This work consists of dewatering work sites.

906.2Materials.

A.Portable Sediment Tank. Provide materials for portable sediment tanks as follows:
1.Wire Mesh - 23-gauge wire steel or galvanized welded wire reinforcement with openings 1/4 -

inch by 1/4 -inch.

2.Corrugated Metal Pipe
3.Geotextile Section 1060
4.Fasteners ASTM F541, Type 1 or Type 2
5.Metal Plate - 1/2-inch thick
B.Approved equal sediment tank
C.Dewatering Bag.

Use in accordance with the manufacture’s recommendations with a performance requirement retaining soil particles on a #80 sieve, 177 microns.

D.Sump Pit.
1.Coarse Aggregate , No. 57 Stone Section 1004
2.Corrugated Metal Pipe
3.Geotextile Section 1060
4.Wire Mesh – 23-gauge steel or galvanized welded wire reinforcement with openings 1/4 -inch by

1/4-inch.

5.Approved equal sump pit
E.Skimmer dewatering device
1.Coarse Aggregate , No. 57 Stone Section 1004
2.Pipe Culverts , PVC Section 1031
3.Reinforcing Steel Section 1037
F.Well Point System
1.Coarse Aggregate Section 1004
2.Pipe Culverts Section 1031
3.Reinforcing Steel Section 1037

906.3Construction

DEWATERING PRACTICES SECTION 906 586 A. Trap and filter water produced by dewatering activities. Pump to a suitable discharge area. Trap and retain sediment before discharging water into drainage ways, adjoining properties, and rights - of-way below a project site.

B.Use dewatering practices shown in the contract. If the contract or the engineer do not specify a

specific dewatering practice, use a dewatering practice listed below that is appropriate for the specific situation. The engineer’s approval is needed to us e dewatering practices not included in this list.

C.Inspect weekly and immediately after every rainfall to maintain and make repairs as needed.
D.Portable Sediment Tank
1.Construction
a.Construct the portable sediment tank according to the Standard Construction Details.

Construct an approved equal portable sediment tank in accordance with the manufacturer’s instructions.

i.The maximum allowable pump discharge of the typical portable sediment tank is 125

gallons per minute.

b.Locate the tank on a level surface and in an area where the tank will cause minimal

interference with construction activities, and vehicular and pedestrian traffic.

c.Obtain the engineer’s approval to locate the portable sediment tank at a different location,

within the LOC, than what is shown in the contract.

d.Construct watertight welds.
e.Fasten the wire mesh and geotextile to the pipe.
2.Maintenance
a.Remove sediment when it accumulates to a depth of 1/3 of the portable sediment tank

height.

b.Remove and replace the filter geotextile when:
i.It allows the portable sediment tank to exceed the maximum allowable discharge flow rate

of 125 gallons per minute ; ii. when there is a tear; and iii. when directed by the engineer.

c.Dispose of all sediment collected in the portable sediment tank in an approved disposal area.
3.Removal
a.After removal, grade the area to match the contours shown in the contract. If no contours are

shown, match the grades that existed before construction of the tank.

b.Stabilize areas affected by the portable sediment tank in accordance with Section 908.
E.Dewatering Bag
1.Construction

DEWATERING PRACTICES SECTION 906 587 a. Place dewatering bags at locations designated in the contract in accordance with the manufacture’s recommendations, or as approved by the engineer.

b.Maintain a water -tight connection.
c.Secure in place.
d.Do not exceed the manufacturer's recommended flow rate or capacity.
e.Discharge the dewatering effluent without causing erosion. The engineer will approve the

types of erosion control measures if needed.

2.Maintenance

Provide and place a new dewatering bag in accordance with the manufacture’s recommendations or as determined by the engineer.

3.Dewatering Bag Removal
a.Remove and dispose of a dewatering bag when replaced or when no longer needed.
b.Regrade the area to match the contours shown in the contract. If no contours are shown,

match the grades that existed before dewatering bag construction.

c.Stabilize areas affected by the dewatering bag in accordance with Section 908.
F.Sump Pit.
1.Construction
a.Excavate the sump pit according to the dimensions in the Standard Construction Details or in

accordance with the manufacture’s recommendations.

b.Place the layer of stone in the bottom of the sump pit in accordance with the Standard

Construction Details. Place the stationary pipe with a bottom cap on top of the bottom layer of stone.

c.Place the removable pipe inside of the stationary pipe in accordance with the Standard

Construction Details. Extend both pipes to the same height and a minimum of 12 inches above the lip of the sump pit.

d.Backfill the sump pit with stone.
e.Slope the stone to meet the height of the pipes.
2.Maintenance

When clogged with sediment, replace the geotextile and, if applicable, the wire mesh on the removable pipe and bottom cap.

3.Removal
a.Remove the sump pit and regrade the area to match the contours shown in the contract. If the

contract does not show contours, match the grades that existed before construction of the sump pit.

b.Stabilize all areas affected by the sump pit, if needed, in accordance with Section 908.
G.Skimmer Dewatering Device
1.Construction

DEWATERING PRACTICES SECTION 906 588 Construct skimmer dewatering devices in accordance with the dimensions in the Standard Construction Details and place at the locations shown in the contract.

2.Maintenance

Maintain the skimmer dewatering device in proper operational condition while required on the project.

3.Removal

Remove the skimmer dewatering device from the project site when directed by the engineer.

H.Well Point System

A typical well point system consists of a series of small diameter wells connected via a header pipe to the suction side of a suitable well point pump.

1.Construction
a.Design a well point system capable of controlling groundwater in order to install proposed

structures on a dry and stable sub -base. Select a location for installing the well point system that will not interfere with construction of the proposed structur e until removal is appropriate. If inclusion of the well point system in the work area requires modifications to construction phasing, include the modifications in the shop drawings.

b.Obtain and comply with all necessary permits in accordance with Section 902. Obtain permits

and provide copies to the engineer before beginning excavation.

c.Install and test the well point system in accordance with the approved design to demonstrate

the system's effectiveness to the engineer’s satisfaction before continuing with the excavation.

d.Modify the well point system if it cannot maintain the groundwater elevation required to

provide a dry and stable sub -base.

2.Maintenance

Maintain the well point system to ensure working order and continuous drawdown throughout the dewatering process.

3.Removal
a.Remove the well point system after placement of all proposed structures and backfill affected

by groundwater conditions, or as directed by the engineer.

b.Stabilize areas affected by the well point system, if needed, in accordance with Section 908.

906.4Method of Measurement.

A.The Department will measure the quantity of dewatering work completed and accepted as

follows:

1.Portable sediment tanks by each placed and accepted.
2.Dewatering bag by each placed and accepted.
3.Sump pit by each placed and accepted.
4.Skimmer dewatering device by each constructed, placed and accepted.
Source: Delaware Standard Specifications for Road and Bridge Construction, 2025 Edition. Pages 595598 of 779.