211000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS LS

DE · 2025 Standard SpecificationsBook pages 137138View official source ↗

REMOVAL OF STRUCTURES AND OBSTRUCTIONS SECTION 211 127 The Department will pay for removal of structures and obstructions, removal of PCC pavement, curb, and sidewalk, and removal of guardrail and fence at the contract unit price. Price and payment will constitute full compensation for removing and disposing of structures and obstructions, PCC pavement, curb, and sidewalk , and guardrail and fence designated for removal. The Department will not make separate payment for excavating, backfilling, and compacting cavities resulting from structure removals or salvaging, storing, and protecting materials in the right -of-way. ITEM DESCRIPTION UNIT 211000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS LS 211001 REMOVAL OF PCC PAVEMENT, CURB , AND SIDEWALK SY 211002 REMOVAL OF GUARDRAIL AND FENCE LF GRADED AGGREGATE BASE COURSE SECTION 301 128 DIVISION 300 — BASE COURSES

301.1Description.

This work consists of constructing GABC on a prepared subgrade or subbase.

301.2Materials.

A.Coarse Aggregate Section 1004
B.Graded Aggregate Section 1005

301.3Construction.

A.Shape the subgrade to grade and cross section in accordance with the contract and Section

202.3.5.

B.Place material so that no segregation occurs. Use a water sprinkling device and rollers or

compactors.

C.Place graded aggregate material in successive layers, with a maximum layer thickness of 8

uncompacted inches to prevent segregation and with a maximum surface deviation of 1/2 -inch in 10-feet.

D.Compact each layer to 98 percent or more of the laboratory maximum density in accordance with

AASHTO T99 Method C, Modified, and T310.

1.If bituminous millings are used as GABC within the roadway pavement box, compact with a

sheepsfoot roller to the satisfaction of the engineer.

E.When using GABC from different sources, keep materials for a single project in separate

stockpiles. The contractor and engineer must agree on placement limits when the contractor plans to use multiple material sources. Ensure that each area of base course constructed is from a single source for full depth placement within agreed limits.

F.The Department will not allow Recycled Concrete Aggregates (RCA) as the final project surface.

301.4Method of Measurement.

A.The Department will measure the total quantity of material from all sources as the number of

cubic yards or tons of GABC placed and accepted. The Department will determine weight in accordance with Section 109.1.

B.Refer to the Department’s Material Average Weight Chart for conversion factors from cubic yards

to tons for the respective material.

301.5Basis of Payment .

A.The Department will pay for GABC and recycled material at the contract unit price per cubic yard

or ton for preparing, providing, placing, and compacting all materials . The Department will make no additional payment for work performed to bring recycled concrete aggregate or bituminous concrete millings into compliance with requirements specified in Section 1005.

Source: Delaware Standard Specifications for Road and Bridge Construction, 2025 Edition. Pages 137138 of 779.