SERVICE PEDESTAL AND SAFETY SWITCH SECTION 842
519 SECTION 842 — SERVICE PEDESTAL AND SAFETY SWITCH
842.1Description.
This work consists of providing and installing or removing lighting and traffic service pedestals and safety switches.
842.2Materials.
842.3Construction.
standards, and with utility company minimum requirements.
Fuse and size the line side safety switch to service.
devices the switches serve:
ii. Signal. iii. Camera. iv. Repeater.
vi. Detector. vii. RWIS denoting the device it serves.
pattern or remove the concrete to the nearest joint. SERVICE PEDESTAL AND SAFETY SWITCH SECTION 842
520 3. Place Conduit.
safety switch and meter.
degree sweeps at the base of the pedestal board. Ensure that the conduit extends 3 -feet above the surrounding grade.
footings with 25 -pounds of concrete at each leg, just below grade and as directed by the engineer .
height of the meter and the safety switch.
include all lighting system work including service, branch circuits, junction wells, underground conduit, and all grounding and bonding: Provide certification documentation for the Delaware -licensed electrical inspection agency to the engineer for approval before starting work.
the engineer.
by the contract and as directed by the by the engineer.
by the contract and as directed by the by the engineer.
842.4Method of Measurement.
The Department will measure the quantity of electric services as the actual number installed and accepted.
842.5Basis of Payment.
The Department will pay for the quantity of electric services at the contract unit price for each installed and accepted. Price and payment constitute full compensation for all materials, installation, and inspection by a Delaware licensed electrical agency. ITEM DESCRIPTION UNIT 842001 ELECTRIC SERVICE ON WOOD POLE EA 842002 ELECTRIC SERVICE ON METAL POLE EA SERVICE PEDESTAL AND SAFETY SWITCH SECTION 842
521 ITEM DESCRIPTION UNIT 842003 ELECTRIC SERVICE ON PEDESTAL EA 842004 ELECTRIC SERVICE ON PEDESTAL WITH SERVICE RISER EA 842005 REMOVAL OF ELECTRIC SERVICE ON WOOD OR METAL POLE EA 842006 PROVIDE AND INSTALL EMBEDDED METERED SERVICE PEDESTAL (100 AMP) EA 842007 PROVIDE AND INSTALL ELECTRICAL UTILITY SERVICE EQUIPMENT 120/240 EA
HIGHWAY LIGHTING ELECTRICAL TESTING SECTION 843
522 SECTION 843 — HIGHWAY LIGHTING ELECTRICAL TESTING
843.1Description.
This work consists of electrical testing for highway lighting systems .
843.2Materials.
Not applicable.
843.3Construction.
include a 1 -year warranty of the highway lighting system installed under the contract. The highway lighting system includes all items of work performed under the contract to provide lighting of roadways, bike paths, parking lots, or other areas.
junction wells, cables, load centers, transformers, cabinet pads, pole bases, poles, high mast poles, light standards with and without davit arms, luminaires, service installations, and reworked or relocated existing lighting facilities.
requirements, state and local laws, and ordinances governing the work.
Submit a copy of the master electrician’s license to the engineer for approval.
local regulations.
electrical installations.
beginning each test. Include a written certification stating when the testing equipment was last calibrated. Ensure the calibration date is within 180 calendar days of the date of testing. Perform all tests in the presence of the engineer. 843.3.1 Ground Resistance Testing.
earth tester with a 0.50 to 500-ohm scale or digital read -out. Ensure the resistance is 25-ohms or less.
Perform the test when the soil is dry. Do not add any chemical or salt solutions to any portion of the grounding system.
unless otherwise determined by the engineer. Drive 2 auxiliary copper clad ground rods into the ground a minimum of 3 -feet apart.
approve the spacing. Isolate each ground rod or foundation ground with the bond wires disconnected when performing the test. Ensure the resistance to groun d is 25 -ohms or less. Perform 2 ground resistance tests unless noted otherwise in the contract.